7. PUTTING INTO SERVICE

7.1 FINAL CHECKS

1. Make sure that the forces generated by the gate
are within the limits permitted by the current
regulations. Use an impact force tester in ac-
cordance with EN 12453. For non-EU countries,
of there are no specific local regulations, the force
must be less than 150 N.
adjustments that may be needed by referring also
to the operator instructions.
2. Carry out a complete functional test of the automa-
tion and all the installed devices.
3. Refer to the operator instructions for any additional
tests that may be required.

7.2 CLOSE THE ENCLOSURE

Close the enclosure in which the board is housed by
referring to the specific instructions.

7.3 FINAL OPERATIONS

Make sure that the system delivery requirements
have been fulfilled (otherwise arrange for them) i.e.
that they correspond to the board installed / replaced.
FSW
OP/CL
FSW
E045S
If necessary, make any
CL
FSW
OP
3

8. ACCESSORIES

8.1 BUS 2EASY DEVICES

It is possible to connect FAAC BUS 2easy devices (pho-
tocells, sensitive edges, control devices) to this board.
i
If no BUS 2easy accessories are used, leave connector
J10 free. Do not bridge.

CONNECTION

Connecting the BUS 2easy devices to connector J10.
i
The overall length of the BUS 2easy cables must not
exceed 100 m.
The BUS line does not require a matching polarity
connection (apart from the encoder connection, see
specific section).
BUS
2 Easy
2EASY
J10

BUS 2EASY PHOTOCELLS

!
Photocells are additional type D detection devices
(according to EN 12453) that reduce the likelihood of
contact with the moving leaf. The photocells are not
safety devices according to standard EN 12978. De-
tection devices used as safety accessories (e.g. sensi-
tive edges) to protect against a hazard, must comply
with standard EN 12978.
Type of use (3):
Photocell active during closing
FSW CL
Photocell active during opening
FSW OP
FSW OP/CL Photocell always active
Photocell for OPEN A
OPEN
i
The action carried out when the photocells are trig-
gered depends on the operating logic selected.
1. Assign an address to the BUS 2easy photocells by
setting the four DIP switches on both the transmit-
ter and the corresponding receiver.
17
BUS
BUS
2 Easy
2 Easy
532373 - Rev.A