Commissioning
⇒
ENDRESS + HAUSER
–
+
E
42
6
Commissioning
6.1
Function check
Make sure that all final checks have been completed before you start up your measuring point:
• Checklist "Post-installation check" (→ ä 25).
• Checklist "Post-connection check" (→ ä 25).
6.2
Switching on the measuring device
When the instrument is switched on for the first time, the following messages appear on the display:
⇓
⇓
⇓
⇓
⇓
⇓
Levelflex M FMP45 with HART/4...20 mA
After 5 s, the following message appears
After 5 s, the following message appears (e.g. on HART
devices)
After 5 s or after you have pressed
message appears
Select the language
(this message appears the first time the instrument is
switched on)
Select the basic unit
(this message appears the first time the instrument is
switched on)
The current measured value is displayed
F
After
is pressed, you reach the group selection.
This selection enables you to perform the basic setup
F
the following
Endress + Hauser