Table 2-4, Equipment Grounding Conductor Sizing - Magnum Energy MagnaSine Hybrid Owner's Manual

Renewable energy pure sine wave inverter/charger
Table of Contents

Advertisement

Installation
2.6.2
System Bonding Jumper
The MSH-RE Series inverter does not include an internal bond between the grounded conductor
(AC neutral/DC negative) and the equipment grounding terminals. This bond [system bonding
jumper (SBJ)] is usually done in the main distribution panel for each electrical system.
CAUTION: There should be one and only one point in each electrical system (both
AC and DC) where the grounded conductor is attached to the grounding electrode
conductor.
AC Side – The size of the system bonding jumper (SBJ) in the AC electrical system is based on
the area of the largest AC ungrounded conductor. In accordance with the NEC, use Table 2-4 to
determine the system bonding jumper size compared to the largest AC ungrounded conductor.
DC Side – The size of the system bonding jumper (SBJ) in the DC electrical system must not be
smaller than the DC grounding electrode conductor (GEC–DC) used, which is determined from the
grounding method that will be used (see Section 2.6.1).
2.6.3
Equipment Grounding Conductor
The inverter case and all other noncurrent-carrying exposed metal surfaces in the entire electrical
system that may be accidentally energized must be grounded. The equipment-grounding conductor
must be sized to safely carry the maximum ground-fault current likely to be imposed on it from
where a ground-fault may occur. In accordance with the NEC, use Table 2-4 to size the equipment-
grounding conductors. This table requires that the equipment-grounding conductor be sized
according to the rating of the overcurrent device protecting the circuit.
CAUTION: The connections and wiring for the equipment-grounding conductor must
be continuous to allow fault currents to properly operate overcurrent devices. Where
equipment is removed and this disconnects the bonding connection between the grounding
electrode conductor and exposed conducting surfaces, a bonding jumper must be installed
while the equipment is removed.
AC Side – Where the AC output from the inverter is connected to an AC load center, there should
be an equipment grounding conductor connected between the inverter case and the grounding
point in the AC load center. The AC equipment grounding conductor (EGC–AC) is sized per Table
2-4 and is connected to the inverter's AC equipment grounding terminal shown in Figure 2-8.
DC Side – Since the currents on the DC side are higher than the AC side (5 times at 24 volts),
the equipment grounding needs are different. The DC equipment grounding conductor (EGC–DC)
is sized per Table 2-4 and connected to the DC equipment grounding terminal on the inverter as
shown in Item 7, Figure 1-2.

Table 2-4, Equipment Grounding Conductor Sizing

Page 26
Rating of Overcurrent
Device
15 amps
20 amps
30 - 60 amps
100 amps
200 amps
300 amps
400 amps
Minimum Size of Copper
Ground Wire
#14 AWG (2.1 mm
#12 AWG (3.3 mm
#10 AWG (5.3 mm
#8 AWG (8.4 mm
#6 AWG (13.3 mm
#4 AWG (21.1 mm
#3 AWG (26.7 mm
© 2013 Magnum Energy, Inc.
)
2
)
2
)
2
)
2
)
2
)
2
)
2

Advertisement

Table of Contents
loading

This manual is also suitable for:

Msh4024re

Table of Contents