Halton Safe Management 2.0 (SM2) - Installation, commissioning, operating, and maintenance guide
4 Installation
4.1 Before you start
4.1.1 Safety during installation
4.1.2 Installation process
The main steps in the installation process are the following:
▪ Determining the installation places from the design drawings.
▪ Installing the components applicable for the project.
▪ Connecting the wiring.
▪ Connecting the system to power.
1.0
ELECTRIC SHOCK HAZARD
Before carrying out any electrical work, turn off the power to avoid injury from electrical
current.
FALLING HAZARD
Pay special attention and use proper equipment when working at height.
PERSONAL INJURY HAZARD
Follow all local health and safety regulations and use proper personal protective
equipment.
NOTICE
All installation, commissioning, and maintenance work must only be carried out by
qualified personnel.
NOTICE
All electrical work must only be carried out by qualified personnel.