After the processor has turned ON, start-up screens similar to the following will be displayed one after
another:
NOTE:
The name displayed on the second INTERNAL SELF TEST screen will correspond with the processor you are
using.
After the INTERNAL SELF TEST, if the feature is enabled, the TRACEABILITY screen will be displayed, allowing
you to enter Operator Traceability Data. If this screen appears, see page 42 for instructions how to enter the
data.
After the Operator Traceability Data is entered, the processor will display the CONNECT FITTING screen.
Examples of the CONNECT FITTING screen are shown below:
AC Powered Processors
CONNECT FITTING
Temperature:
Gen:
120V
The second line indicates the ambient temperature the processor is measuring and will be used to modify the
fusion time if required by the fitting manufacturer.
Check to make sure the temperature reading is accurate. If the processor has been in direct sunlight or has
been moved from a hot or cold environment, the temperature may not be correct. If the temperature
indicated is not correct, allow the processor time to adapt to the correct temperature, approximately 15-20
minutes.
The last line indicates the status of the processor's power source. If operating an AC Powered Processor, the
voltage and frequency of the generator are displayed. If operating a Battery Powered Processor, the voltage
and charge state of the battery are displayed. It is important that the voltage measurement is within the
allowable range and the frequency is stable, or that the battery state is "OK."

Boot Sequence

INTERNAL SELF TEST
Please wait...
INTERNAL SELF TEST
SHANNON
CAL DUE – 05/11/2021
PASSED
+75° F
60.0Hz
Page 23 of 60
Battery Powered Processors
CONNECT FITTING
Temperature:
Batt:
52.0V
+75° F
OK