VERSION 11/2015
OPERATING MANUAL
6.6
COMMISSIONING
Observe all safety regulations in accordance with Chapter 4 and Chapter 7.2.
Emergency stop, see Chapter 7.3.
Preparation
Before every start-up, the following points should be observed as laid down in the
operating manual:
- Secure gun with safety clip.
- Check the permissible pressures.
- Check all connections for leaks.
- Check hoses for damage in accordance with Chapter 8.2.7.
Fill the pump with fl ushing agent
The devices are tested during manufacturing with emulsifying oil, pure oil or solvent.
Possible residues must be fl ushed out of the circuits with a solvent (fl ushing agent) before
commissioning.
- Fill the separating agent in accordance with Chapter 8.2.4.
- Fill the empty device with fl ushing agent in accordance with Chapter 8.2.6.
Pressure tightness test
- Gradually increase the pressure in pump with the pressure regulator until
maximum pressure is reached. Maintain the pressure for 3 minutes and check all
connection points for leaks.
- Depressurization in accordance with Chapter 7.5.
Filling with working material
- In accordance with Chapter 7.6.1.