1. Connect the AC input plug (1) to a grounded outlet.
2. When first powered up, the charger will go through a
short LED indicator self-test. The battery charger light's
on the Ground Control Station will flash in sequence for
two seconds.
3. The batteries are fully charged when the green light on
the battery charger status panel (Ground Control Sta-
tion) is illuminated.
NOTE: If the charger is left plugged in, the charger will automati-
cally restart a complete charge cycle if the batteries volt-
age drops below a minimum voltage or 30 days has
elapsed.
31210162
– JLG Lift –
SECTION 4 – MACHINE OPERATION
4-15