Figure 3-10
Connecting AC Power and RPS
Á
À
1 AC power cord
2 AC power connector
3.
Observe the power CPU LED (not shown) located on the front panel. During the
initialization, the CPU LED will start by illuminating solid amber, then start blinking
green, then blinking amber, then blinking green again until the end of the
initialization, and then turns solid green.
Note: If the CPU LED illuminates solid red, there was a critical failure. For more
information about the LED indications and troubleshooting, refer to
additional help, contact Enterasys Networks. Refer to
details
.
If the switch is a standalone unit, it will take approximately 30 seconds for the switch
to start up. If the switch is a stack Manager, it can take up to 3 minutes or more to start
up, depending on the number of Member switches in the stack.
Â
3 Connector for external redundant power supply
"Getting
SecureStack B2 Installation Guide 3-15
Connecting AC and PoE Power
Chapter
4. If you need
Help" on page 1-8 for
Need help?
Do you have a question about the SecureStack B2 B2G124-48P and is the answer not in the manual?