Stacking The Sehi - Cabletron Systems HubSTACK SEHI-34 User Manual

10base-t intelligent stackable hub
Hide thumbs Also See for HubSTACK SEHI-34:
Table of Contents

Advertisement

INSTALLATION
Free-standing and shelf installations must be within in reach of the
network cabling and meet the requirements listed below:
A single phase 120Vac, 15A, grounded power receptacle must
be located within 7 feet of the location.
If you use a shelving unit, it must be able to support 30 pounds
of static weight for each device in the stack.
The temperature for the selected location must be maintained
between 5 and 50 C, and fluctuate less than 10 C per hour.
The following sections provide instructions for stacking the SEHI or
installing it as a stand-alone device. Select one of the following
subsections and perform the steps that are applicable to your
installation needs.

3.2.1 Stacking the SEHI

The rear panel of the SEHI has an Interconnect Bus Out Port (male
connector). You daisy chain units together using Cabletron Systems'
HubSTACK Interconnect cables. Table 3-1 describes each cable.
Table 3-1. HubSTACK Interconnect Cables
Part
Number
9380110
9380111
Page 3-2
Description
12" HubSTACK
Interconnect Cable
18" HubSTACK
Interconnect Cable
Application
SEH to SEH connections.
SEHI to SEH connections.