Installation - Jeio tech Lab Companion SK-300 Operating Manual

Shaker
Table of Contents

Advertisement

Installation

The machine should be installed on a safe and proper environment following to the below.
Check Points
Select a proper place
Level off the machine
Power connection
Select a proper place
1. Operating condition: Class 100 ~ Class 10,000 as Clean environment degree for Bio
Clean room is optimal condition for shakers.
Room condition of temperature and humidity should be normal as 18 ℃ ~ 25℃, below
80%RH.
2. Environmental condition: Do not expose the machine to direct ray of light.
3. Setting place: The floor should be on flat and leveled ground.
4. S pace: The machine should be kept at least 1.5m from any illuminators and 20 cm from
walls.
Level off the machine
All of the bottom sides should be leveled.
Page 12
The machine should be operated at the optimum
condition
for
cleanness,
preparation against fire.
electricity
and

Hide quick links:

Advertisement