Transportation & Installation Preparation
4. Attach the hoisting hooks and cables to the steel rings on the inverter.
Crane Hook
Steel Ring
Hoisting Hook
Figure 3-11 : Attaching the Hoisting Cables
5. Attach the crane hook to the steel ring on the hoisting cables.
6. Lift up the inverter and transfer to the installation site steadily.
7. Remove the hoisting cables.
23