GENERAL VALVE INSTALLATION
FIGURE 2. Valve Face O-Ring and Nozzle Control Valve
Valve Body Face
O-Ring
1. Place a supplied o-ring on the inside of the fly nut flush with the valve body face.
2. Thread the fly nut onto the nozzle body.
3. Orient the nozzle control valve so that the label is easily readable.
4. Hand tighten the swivel nut to secure the nozzle control valve to the nozzle body. Do not over tighten.
NOTE:
Frequently check the nozzle control valve nuts to ensure they are secure.
5. Repeat the previous steps to mount a nozzle control valve to each nozzle body on the spray boom.

BOOM CABLE ROUTING AND CONNECTION

For a boom cable routing drawing example, refer to the"System Diagram" on page 17.

BEST PRACTICES AND RECOMMENDATIONS

• Route the AIM Command FLEX primary and secondary boom cables along existing cables or plumbing to help
avoid damage to the cable.
• Route cables to avoid pinch points and to avoid stretching the cable during folding and unfolding operations.
Pay special attention to cable routing near folding or break-away points.
• Route cables through existing cable retention devices as appropriate.
• When securing the primary and secondary boom cables on the implement, begin at the outer boom tips.
Adjust the cable position to provide sufficient slack between valve tee branches while working toward the
center of the implement.
• Route the boom cables on the inside of the boom frame work.

SECONDARY BOOM CABLE ROUTING AND CONNECTIONS

NOTE:
Please review the "System Diagram" on page 17 before routing or securing the boom cables on the
implement. Do not connect or secure the cables until instructed to do so in the procedure.
14
Nozzle Body
AIM Command FLEX, Patriot MY 2017 Installation Manual