Huawei UPS5000-S-1600 kVA User Manual page 68

Table of Contents

Advertisement

UPS5000-S-1600 kVA
User Manual
Figure 3-8 Expansion bolt composition
(1) M12 bolt
Ensure the expansion tube of the expansion bolts fits completely into the hole. The expansion
sleeves must be completely buried under the ground to properly facilitate subsequent
installation.
Figure 3-9 Installing expansion bolts (unit: mm)
1.
2.
3.
4.
Issue 04 (2020-03-03)
(2) Spring washer
Drill holes in the ground by using a hammer drill. The hole depth is 52 mm to 60 mm.
Partially tighten the expansion bolt and vertically insert it into the hole. Hit the
expansion bolt using a rubber mallet until the expansion sleeve is fully inserted into the
hole.
Partially tighten the expansion bolt.
Remove the bolt, spring washer, and flat washer.
Copyright © Huawei Technologies Co., Ltd.
(3) Flat washer
(4) Expansion sleeve
3 Installation
60