Spraying - Graco Reactor 2 Hydraulic Operation

Proportioning systems
Table of Contents

Advertisement

Spraying

Spraying
Spraying
The Fusion AP gun is shown.
1. Engage gun piston safety lock and close gun
luid inlet valves A and B.
Fusion
Fusion
Fusion
2. Attach gun luid manifold. Connect gun air line.
Open air line valve.
3. Adjust the gun air pressure. Do not exceed 130
psi (0.2 MPa, 2 bar).
4. Set PRESSURE RELIEF/SPRAY valves (SA,
SB) to SPRAY
SA
5. Verify heat zones are on and temperatures are
on target, see
Home
334945C
Probler
Probler
Probler
.
GB
GA
SB
System Off, page
6. Open luid inlet valve (FV) located at each pump
inlet.
7. Press
8. Adjust pressure compensator knob to desired
luid stall pressure. Turn knob clockwise to
increase pressure and counter-clockwise to
decrease pressure. Use hydraulic pressure
gauge (HPG) to view hydraulic pressure. Once
desired luid stall pressure is set, lock the knob
in place by rotating lower portion clockwise until
tight.
39.
Component A and B outlet pressures will be
higher than the hydraulic set pressure, depending
on the model. Component A and B (GA, GB)
pressure may be viewed on the pressure gauges
or the ADM.
to start motor and pumps.