ABB ACX Commissioning Instruction page 47

Advanced cga solutions, analyzer system for emission monitoring, cement applications and process measurement
Table of Contents

Advertisement

Analyzer Cabinet Installation
Installing the Analyzer Cabinet
Installing the
Foundation
Unpacking the Analyzer
Cabinet
Setting Up the Analyzer
Cabinet
CI/ACX-EN Rev. D
Observe the installation site requirements, see page 12
Observe the "Layout Plan" in the drawings set.
CAUTION!
The analyzer cabinet weighs approx. 370 to 430 kg.
A suitable lifting device (crane, block and tackle, lifting
truck, etc.) is required for transport, setting upright and
installation!
Use the handling lugs provided to connect any lift cables
to the analyzer cabinet.
The lift cable must be long enough to have an angle of at
least 60° relative to the top of the cabinet when under
tension (see the illustration).
If this is not done the handling lugs can be bent or the
analyzer cabinet can be warped.
It is strongly recommended that the analyzer cabinet is
transported by a specialist firm
transported in a horizontal position as far as possible and
not set upright until immediately before the installation!
Lift out the analyzer cabinet from the shipping box.
Do not remove the plastic sheet in which the analyzer cabinet is wrapped.
Unpacking a cold analyzer cabinet can lead to condensation.
Do not remove the plastic film until just before the analyzer cabinet will be
connected and it has reached room temperature. This takes at least 24 hours.
Installation site requirements, see page 12
Material required, see page 24
Follow the "Layout Plan" in the drawings set.
Ground by means of the central grounding screw, route the grounding cable
2
(≥ 10 mm
/ AWG 6) through the M16 cable gland.
ACX Analyzer System Commissioning Instruction