Required System Components; Other Items - enphase C250 Installation And Operation Manual

Microinverter system
Hide thumbs Also See for C250:
Table of Contents

Advertisement

Required System Components

You need the following components to install the C250 system:
Enphase C250 Microinverter: (model C250-72-2LN-S2 or C250-72-2LN-S5)
Enphase Envoy-C Communications Gateway: (model ENV-C250). The Envoy has a 250V-
rated, NEMA 6-15P plug. The receptacle must be NEMA 6-15R.
NOTE: The C250 Microinverter works only with the Envoy-C (model ENV-C250).
Enphase Engage Cable:
Model number
ET10-277-BULK
ET17-277-BULK
ET21-277-192-12AWG Landscape, 72-cell modules
For more information, see "Engage Cable Planning and Ordering" on page 32.
Transformer: The transformer must adapt the utility voltage (usually 480Y/277V) to no more
than 248V line-to-neutral for connection to the Envoy-C and C250 Microinverters.
Surge protection device(s).
Phase Coupler
Enphase Line Filters (model LCF-250-PC), for additional Envoys, if needed.

Other Items

Cable clips (model ET-CLIP-100)
Sealing caps, as needed (model ET-SEAL-10). One needed for each unused drop on the
Engage Cable.
Terminators, as needed (model ET-TERM-10). One needed at the end of each AC branch
circuit.
Enphase disconnect tool (model ET-DISC-05). You can substitute numbers 2 and 3 Phillips
screwdrivers.
Engage Couplers (splice kits), as needed. (ET-SPLK-05)
Commercial grade NEMA 6-15R receptacle required for each Envoy
Outdoor-rated, weather-proof AC junction box(es)
Gland or strain relief fitting (one per AC junction box)
Number 2 and 3 Phillips screwdrivers
Torque wrench, sockets, wrenches for mounting hardware
Adjustable wrench or open-ended wrench (for terminators)
Handheld mirror (to view LEDs on the undersides of the microinverters)
Laptop or mobile device for Envoy set up (recommended)
Bluetooth scanner for use with Enphase Installer Toolkit
13
PV module orientation
Portrait, 60- and 72-cell modules
Landscape, 60-cell modules
 2015 Enphase Energy Inc. All rights reserved.
C250 System Installation and Operation
141-00025 Rev 03

Advertisement

Table of Contents
loading

This manual is also suitable for:

C250-72-2ln-s2C250-72-2ln-s5

Table of Contents