Starter Replacement Procedure

1. Required parts and tools used

Part names and tools used
Starter
Torque wrench
Socket wrench set
Extension bar
Box wrenches
General tools

2. Preparation for work

(1) See "1. Safety Precautions" and "2. Preparation for
work" of "Basic Operation" in this manual.

3. Remove starter

(1) Remove the wires for the B and S terminal
connectors on the starter, as shown in Figure 1.
B terminal nut
(width across at)
(2) Remove the bolts indicated by arrows in Figure 2
that are securing the starter. Remove the starter.
Bolt (width across at)

4. Install starter

The starter installation procedure is the reverse of the
removal procedure.
(1) Install the starter by tightening the bolts in Figure 2
that secure the starter.
Tightening torque
(2) Reconnect the wires for the B and S terminal
connectors on the starter, as shown in Figure 1.
Tightening torque

5. Preparation for operation

(1) Turn on the power supply circuit breaker for the
outdoor unit.
(2) Open the main gas valve, starting the fuel supply.
(3) Set the STOP SW (S001) from STOP to NORM.
(Figure 3)

6. Final check

(1)Running condition check
Make sure that no abnormal noise or vibration occurs.
Make sure that none of the attached parts are loose.
Parts code and use
623-166-9511
9.8 ~ 11.8 N · m
32.4 ~ 38.2 N · m
1 set
Approx. 150 mm long
Width across the at: 13 mm and 14 mm
1 set
13 [mm]
14 [mm]
32. 4 ~ 38.2 [N·m]
9.8 ~ 11.8 [N·m]
21
S terminal connector
S terminal connector
Figure
Figure
.1
.1
Figure
Figure
.2
.2
Figure
Figure
.3
.3
B terminal
B terminal
Starter securing bolts
Starter securing bolts

Advertisement

Table of Contents
loading

Table of Contents