Installing and removing power components

Advertisement

Installing and Removing Power Components
Figure 32: DC Power Shelf Cable Wiring for Modular Configuration Power Shelf
Note
When wiring the power shelf, be sure to connect the chassis ground cable and install auxiliary grounding
brackets first. For more information, see
Grounding
Caution
Do not connect the ground cables directly to the modular configuration power shelf. For more information,
see
Installing Power Shelf Grounding
Prerequisites
Before performing this task, ensure that both power shelves are installed in the chassis. Remove the upper
grille from the rear (MSC) side of the chassis, if installed.
Note
Before installing wiring on the power shelf, make sure that the input power cables are not energized.
Required Tools and Equipment
• ESD-preventive wrist strap
• Crimping tool and lug specific die
• 3/8 in. ratchet wrench with 10-mm socket
Brackets.
Brackets.
Bonding and Grounding Guidelines
Installing and Removing Power Components
Prerequisites
and
Installing Power Shelf
59