Download Print this page

Cisco CRS-16 DC Installing And Removing page 25

Installing and removing power components

Advertisement

Installing and Removing Power Components
The figure shows the cable wiring for the fixed configuration power shelf.
Figure 14: DC Power Shelf Cable Wiring for Fixed Configuration Power Shelf
Note
When wiring the power shelf, be sure to connect the ground cable first.
Prerequisites
Before performing this task, ensure that both power shelves are installed in the chassis. Remove the upper air
grille on the rear [MSC] side of the chassis, if installed.
Note
Before installing wiring on the power shelf, make sure that the input power cables are not energized.
Note
If cables are wrapped with black electrical tape, be sure to remove tape from cables before installing wiring
on the power shelf.
Required Tools and Equipment
You need the following tools to perform this task:
• ESD-preventive wrist strap
• 3/8 in. ratchet wrench with 10-mm socket
• Crimping tool and lug specific die
• Multimeter
• Torque wrench with 10-mm 6 pt. socket and rated accuracy at 30 in.-lb (3.39 N-m)
• Torque wrench with 10-mm 6 pt. socket and rated accuracy at 20 in.-lb (2.26 N-m)
Installing and Removing Power Components
Prerequisites
25

Advertisement

loading

This manual is also suitable for:

Crs-16 ac