SLB Connection Workflow

WARNING: Connect load cables to the load bank before connection to batteries. If connected
to batteries first and the ends of the cables touch, an arc flash will occur due to a returned
1. Connect load cables to the back of the load bank and then to the battery bank
2. Connect the voltage sensing leads
3. Optional: If using DAC, connect to battery system
4. Connect antenna
5. Power unit ON
6. Optional: Setup software
7. Flip breakers ON
8. Setup discharge testing parameters and begin test
Connection of load cables
Connect the locking quick connect of the black load cable with the black port of the load
bank and the other end (with clamp or direct bolt) with the negative pole of the battery
string.
Repeat this process with the red load cable by connecting one end of the red load cable
with the red port of the load bank and the other end with the positive pole of the battery
string.
Connection with Clamps
Connection of voltage test leads
Connect the round connector of the voltage testing lead to the voltage socket of the load
bank, and the other two clamps with the positive and negative poles of the battery string.
Find Quality Products Online at:
GlobalTestSupply
www.
SLB-Series User Manual
Connection without Clamps
.com
sales@GlobalTestSupply.com
12

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents