Site Preparation

Required Materials Provided by Customer

PN: 1725-36126-001_K.doc
The following steps must be completed before installing the system
hardware. If the steps are not already completed refer to each
individual section for details.
1. At the local site, install and test Primary Shelf and Expansion
Shelves. Refer to SpectraLink 6300 MCU: Installation for
information.
2. At the remote site:
a. Install a two pair cable to each Base Station as designated on
the building floor plans.
b. Terminate the Base Station wiring with RJ-45 crimp-on plugs
at the designated Base Station locations.
c. Terminate the Base Station wire at the appropriate cross-
connect demarc blocks.
d. Terminate the analog or digital phone extensions from the
phone system at the appropriate cross-connect demarc block,
and label the block.
Rack The shelves are designed to fit into a 19" mounting rack.
Each shelf measures 15" high x 19" wide x 9" deep, and weighs
approximately 35 pounds fully loaded. See Chapter 4 Site
Preparation - Prepare Location for Shelves, in the SpectraLink 6300
MCU: Installation document.
Backboard space As an alternative to rack mounting, the shelves
can be wall mounted to 3/4" plywood securely screwed to a wall.
Screws Required to mount the shelves to the wall, or to secure it
in the rack. For wall mount, six #10-5/8" panhead wood screws
(or similar device) are required. For rack mount, screws required
are determined by the rack requirements; typically 10-32 or 1/4-
20.
2