13.3

System test

13.4

Commissioning validation

Building Technologies
Fire Safety & Security Products
1. check the extinguishing process by automatic and manual activation
2. check display of "Released" condition
3. check the pre-warning time
4. check sounders and warning panels operation
5. check RT-Alarm and RT-Fault
6. check fire controls operation
7. check the mechanical blocking device
8. check "Emergency hold/abort" and/or "Automatic blocked" functions
9. check display of "Loss of agent" condition by opening the corresponding
contacts
Commissioning is completed, when:
-
all functions were checked and system works perfectly
-
each detector was tested
-
RT-Alarm and/or RT-fault works correctly
-
no fault is displayed
-
internal buzzer is not disabled (jumper X3 / XCM1002 = ON)
-
permanent "Level 2" operating access is disabled (jumper X8 / XCM1002 =
OFF)
-
all cylinders are connected and pressure or weight is correct
-
mechanical blocking device is disabled
-
all selector valves are closed (for multi-sector installation only)
-
the responsible person in charge of the installation was trained and informed
Commissioning
63
A6V10257473_b_en_--.doc
01.2010