System Test; Commissioning Validation - Siemens XC1001-A Installation And Maintenance Manual

Extinguishing control unit xc10 series
Hide thumbs Also See for XC1001-A:
Table of Contents

Advertisement

Commissioning
13.3

System test

13.4 Commissioning validation

78
Building Technologies
Fire Safety
1. check the extinguishing process by automatic and manual activation
2. check display of "Released" condition
3. check the pre-discharged warning time
4. check sounders and warning panels operation
5. check RT-Alarm and RT-Fault
6. check fire controls operation
7. check the mechanical blocking device
8. check "Emergency hold/abort" and/or "Automatic blocked" functions
9. check display of "Loss of agent" condition by opening the corresponding
contacts
Commissioning is completed, when:
-
all functions were checked and system works perfectly
-
each detector was tested
-
RT-Alarm and/or RT-fault works correctly
-
no fault is displayed
-
internal buzzer is not disabled (jumper X3 / XCM1002 = ON)
-
permanent "Level 2" operating access is disabled (jumper X8 / XCM1002 =
OFF)
-
all cylinders are connected and pressure or weight is correct
-
mechanical blocking device is disabled
-
all selector valves are closed (for multi-sector installation only)
-
the responsible person in charge of the installation was trained and informed
A6V10257473_e_en_--
2015-03-04