Section 2 - Installation; General; Pre-Installation - FULTON RB Series Installation, Operation And Maintenance Manual

Gas/oil/dual fuel horizontal steam boilers
Table of Contents

Advertisement

Fulton Ltd
2.1

GENERAL

The installation of an RB/RBC series fuel fired steam boiler should be carried out by competent
personnel in accordance with all relevant safety regulations. It is the responsibility of the installer
to ensure that these regulations are complied with.
2.2

PRE-INSTALLATION

Prior to delivery of the boiler, consideration should be given to the following:
(Planning regulations may call for more consents than those listed below, always check with your
Local Planning Authority).
A. Local Planning consents where appropriate.
B. Consideration given to access for delivery and positioning of the boiler.
C. Preparation of a suitable base, which must be able to support the total weight of the system
under operating conditions.
The locations of services to the site required for the system, under operating conditions.
D. Electricity supply, check the loading required/available.
E. Drainage system, check the suitability of the drainage system.
F. Local regulations for discharge into existing drains.
G. Suitable access for delivery and off-loading.
H. Safe access to the plant when installation is complete.
RB-RBC-IOMM-2015-1
INSTALLATION - 2

SECTION 2 - INSTALLATION

Page 3

Hide quick links:

Advertisement

Table of Contents
loading