❷ Installing the saltwater chlorinator

2.1 I Installing the cell

• The cell must be installed on the piping aft er the fi ltering, aft er any measurement sensors and aft er any
heati ng systems.
Installing the saltwater chlorinator only
(Example with eXO® (iQ))
• The cell must always be the last element placed on the pool return pipe (see diagram).
• It is always recommended to install the cell on a by-pass. This assembly is MANDATORY if the
fl ow is in excess of 18 m³/hour to avoid head loss.
• If you installed the cell on a by-pass, it is recommended to fi t a check valve downstream from
the cell and not a manual valve, to avoid any risk of incorrect setti ng which could cause poor
circulati on in the cell.
2.1.1 eXO® (iQ) cell
• Make sure that the cell is placed HORIZONTALLY. The water should fl ow from the electric connecti ons
towards the opposite side.
• Use the screw-on fi tti ngs to fi x the cell to the pipes.
• For 63 mm pipes, glue them directly to the screw-on fi tti ngs. For 50 mm pipes, use glue-on PVC adapters of
the corresponding diameter (grey models; the white models are for 1 ½'' UK pipes).
• Connect the cell power cord following the wire colour codes (red, black and blue connectors) and then refi t
the protecti ve cap. The two red wires can be connected to one or the other red terminals on the electrode.
Installing the chlorinator + opti onal module
(Example with eXO® (iQ))
11 cm
15,5
cm
12.5 cm
21,5 cm
32 cm
11 cm
21,5
cm
21,5 cm