Fig.32
Adjusting screw
7.4

Final instructions

Fig.33
Example filled-in sticker
Adjusted for / Réglée pour /
Ingesteld op / Eingestellt auf
/ Regolato per / Ajustado
para / Ρυθμισμένο για /
Nastawiony na / настроен
для / Reglat pentru /
настроен за / ayarlanmıştır /
Nastavljen za / beállítva/
Nastaveno pro / Asetettu
kaasulle / Justert for/
indstillet til/ ‫: ل طبض‬
G20
Gas
20
mbar
C
(10)3(X)
C
(12)3(X)
114494 - v.05 - 06022018
AD-3000111-01
Parameters / Paramètres /
Parameter / Parametri /
Parámetros / Παράμετροι /
Parametry / Параметры /
Parametrii / Параметри /
Parametreler / Paraméterek
/ Parametrit / Parametere /
Parametre / ‫: تاملعملا‬
DP003 - 3300
GP007 - 3300
GP008 - 2150
GP009 -
AD-3001124-01
5. Using the adjusting screw, set the percentage of O
type being used to the nominal value. This should always be inside
the highest and lowest setting limit. The direction in which the ad­
justment screw must be turned to increase or decrease the gas flow
is indicated on the gas valve unit.
6. Check the flame through the inspection window.
Important
The flame must not blow off.
7. Repeat the full load test and the part load test as often as necessary
until the correct values are obtained.
8. Set the boiler back to the normal operating status.
1. Remove the measuring equipment.
2. Screw the cap on to the flue gas measuring point.
3. Seal the gas valve unit.
4. Put the front casing back.
5. Heat the central heating system up to approximately 70°C.
6. Switch the boiler off.
7. Vent the central heating system after approx. 10 minutes.
8. Turn on the boiler.
9. Check the water pressure. If necessary, top up the central heating
system.
10. Fill in the following data on the sticker included, and attach it next to
the data plate on the appliance.
The gas supply pressure;
If set to overpressure application, fill in the type;
The parameters modified for the changes mentioned above.
11. Instruct the user in the operation of the system, boiler and controller.
12. Inform the user of the maintenance to be performed.
13. Hand over all manuals to the user.
14. Confirm the commissioning with a signature and a company stamp.
The boiler is now ready for operation.