1. Installation
1.2

Configuring the field bus node

1.2.1 Setting the field bus node

Festo P.BE−CP−FB13−E−EN en 0802h
Rotary and DIL switches can be found under the cover on the
field bus node (see Fig. 1/1).
Open and close the cover as follows:
Opening: Remove the 2 screws in the cover. Lift up the
·
cover.
Closing: Place the cover in position and tighten the screws
·
by hand.
Caution
Tighten the screws of the switch cover only by hand.
With the rotary and DIL switches you can set the following
functions:
the station number
the voltage monitoring
the field bus protocol PROFIBUS−DP:
Switch elements 3...6 are reserved and must be set to the
positions specified below.
1−5