Installation and commissioning
BASCP_EN
V08 | 08.2018
Installation
Unpacking machine
Read the "Setting up the coffee machine" and "Power supply" chapters carefully before install-
ing.
► Unpack the machine.
► Check the remaining package contents for accessories.
► Remove the accessories supplied in the grounds container and water tank.
► Keep the original packaging in case the equipment needs to be returned.
Power supply connection
Option 1: SCP to 3 kW
► Insert the power cable plug into the lower back of the machine.
► Insert the power plug into the building power socket.
The machine is ready to be switched on.
Option 2: SCP with 6 kW
The machine is equipped with a permanent cable connection at the factory. On the building
side, the machine is connected to the power socket by means of a country-specific plug or an
upstream main switch.
► Insert the power plug into the building power socket or switch on the upstream main switch.
The machine is switched on.
The main screen appears, and the machine begins to heat up.
The machine is ready to use as soon as the required temperature is reached.
When the machine is switched on for the first time, a display-guided adjustment of the machine
configuration follows automatically.
Automatic commissioning program
The commissioning program automatically starts the first time the machine is switched on. It
explains all aspects of installation.
See Chapter "Operation" - "Switching on" for a description on how to switch on the coffee ma-
chine.
www.schaerer.com
25
Need help?
Do you have a question about the Coffee Prime and is the answer not in the manual?