Section 3

OVERVIEW

STARTUP

STARTUP SERVICE

http://www.raihome.com
Startup and Calibration
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . page 3-1
Startup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . page 3-1
Startup Service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . page 3-1
Beam Alignment Procedure . . . . . . . . . . . . . . . . . . . . . . . . page 3-2
Stack / Exit Correlation . . . . . . . . . . . . . . . . . . . . . . . . . . . . page 3-3
Initial Adjustments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . page 3-4
This section covers the OPM 3000 equipment startup procedure and the
adjustments and alignments required prior to initial operation of the system.
Read the entire manual to familiarize yourself with the instrument before attempting these
alignment and calibration procedures.
You must complete the following startup tasks before commencing OPM 3000
monitor operations.
1. Measure and record flange-to-flange distance for use in future off-line
calibration procedures.
2. The air purge and weather cover system, transceiver, and retro
reflector must be installed and power applied.
3. All OPM 3000 wiring and mechanical installations must be completed.
All wiring must be checked.
NOTE
If you are planning to use a recorder, DAS, etc., DO NOT CONNECT THEM
NOW. Outputs and inputs from other sources should be left off until system
has been completely checked according to the instructions in this section. You
should connect and test the customer's external equipment after the proper
function and operation of the OPM 3000 system has been verified.
4. To start up the OPM 3000 apply 115 VAC and 24 VDC power to the
control unit. Observe the control unit display for indications of proper
equipment operation. Refer to Section 4: Normal Operation.
5. Connect the control unit to the customer's equipment as applicable.
Emerson Process Management is available to assist you; call our Customer
Support Center (CSC) at 1-800-433-6076 for details and to schedule startup.