ABB ACF5000 Manual page 41

Multi-component ftir analyzer system
Table of Contents

Advertisement

CAUTION!
ACF5000 FTIR ANALYZER SYSTEM
Do not connect the sample gas line to the sample gas inlet on the ASP block
yet! This connection is made by ABB personnel during the commissioning
procedure.
First connect a PTFE tube of approx. 0.5 m in length to the sample gas inlet 2
on the ASP block. Ambient air will then be sucked into the analyzer cabinet
from outside once the FTIR spectrometer is powered up.
The inlet for the water steam generator 1 on the ASP block must be closed by
means of a blanking plug.
1
Inlet for the water vapor generator
Pressure sensor
2
Connect the electrical leads on the sample gas line as per the "Wiring
diagram" and "Terminal diagram" in the system documentation.
|
OI/ACF5000-EN REV. A
41