ABB ACF5000 Manual page 36

Multi-component ftir analyzer system
Table of Contents

Advertisement

36
"2nd measuring location" option
ACF5000 FTIR ANALYZER SYSTEM
Installing the electrical distributor cabinet
The electrical distributor cabinet for connecting the 2nd measuring location
must be installed as close to the analyzer cabinet as possible.
On the analyzer cabinet, cables of about 5 m in length are applied for con-
nection to the electric distribution cabinet.
Installing the heated switchover valve
The heated 3/2-way solenoid valve for switching between the two measur-
ing locations must be assembled as close to the analyzer cabinet as possi-
ble.
The sample gas lines from the two sampling points and the 1.5 m sample gas
line to the analyzer cabinet must be connected to the switchover valve. Dur-
ing installation of the sample gas lines, the information in the section "In-
stalling the sample gas line" (see page 40) must be observed.
|