Post-Installation Checklist - COMBITHERM CT PROformance Series Installation Manual

Table of Contents

Advertisement

coMbitherM® post installation checKlist
Post installation check sheet power off. Verify all mains before switching CombiOven on for the first time.
Note any non-compliant requirements and correct before turning the CombiOven on.
CUSTOMER INFORMATION:
Date of Installation:
Customer Name:
Model Number:
Serial Number:
CLEARANCES:
Enter the actual measured distances in the boxes provided:
Left:
0" (0mm) required - 18" (457mm) recommended for
service access
Right:
0" (0mm) from non-combustible surfaces; 2" (51mm) for door
swing and away from combustible surfaces
WATER SUPPLY AND DRAINS:
Verify hook up of two (2) separate 3/4" (19mm) diameter cold water lines with 3/4" NPT connection. Verify inlet water
pressure is a minimum of 30 psi dynamic pressure and 90 psi static maximum (2.1 – 6.3 bar)
Alto-Shaam has listed water quality requirements in the installation manual for this equipment. It is the responsibility of the
end user to have the water being connected to this appliance tested to ensure it meets with these standards. Failure to meet with
these standards can void the warranty of the equipment if water quality is found to be the reason of the failure.
Has a filtration system been installed?
Has a complete water Analysis been complete?
Are all water connections 3/4" from main water supply? If no, indicate size and why.
Size/why:
Are all water connections tight?
K Check all lines and connections for leaks, both inside and outside the Combi
ELECTRICAL CONNECTIONS:
Rated Voltage:
Breaker Size:
Actual Voltage:
L1-N
Gas Connections:
Rated Gas Supply:
NOTE: Improper drain connections can result in equipment failure. Alto-Shaam drain requirements are located in the installation
manual for this equipment. Failure to meet these standards can void warranty if the failure is found to have been caused by an
improperly connected drain. It is the responsibility of the installer to ensure the manufactures requirements are met in the plumbing
of the drain system.
DRAIN:
Type of material used for drain?
Does the vertical vent extend above the exhaust opening at the rear of the oven?
Is there a vertical vent within 12" (305mm) of unit drain?
Is there an air gap installed at end of drain run?
Is the drain piped with a positive descending slope?
Use the diagrams provided to create a simple diagram showing how the drain plumbing is ran. Include measurements showing
the distance to the floor drain, location of the air gap, and venting of the drain. Drain plumbing requirements can be found in the
installation manual.
NOTES:
COMBITHERM CT PROFORMANCE AND CT CLASSIC SERIES • INSTALLATION MANUAL • MN-35947 • 60.
K YES
K NO
K YES
K NO
K Inspect water connections inside the Combi
K YES
K NO
Rated Phase:
L2-N
L3-N
Nat
LP
Street Address:
City/State:
Zip:
Back:
4" (102mm) required - 4-5/16" (109mm) for optional plumbing kit
Top:
20" (508mm) required
Type?
Static water pressure:
K YES
K NO
L1-L2
Actual Gas Supplied:
K YES K NO
K YES
K NO
Size of air gap?
K YES
K NO
K YES
K NO
IMPORTANT:
L1-L3
L2-L3
Nat
LP

Advertisement

Table of Contents
loading

Table of Contents