Verifying proper operation

FIGURE 32
1
2
4. If your device has more than one power supply installed, repeat this procedure for each power
5. Verify the device is working properly (refer to

Powering off the system

Verifying proper operation
After you have installed any additional power supplies and powered on the system, verify that the
device is working properly:
1. Verify that the LED for each power supply is a solid green.
2. Verify proper operation by observing the LEDs:
36
DRAFT: BROCADE CONFIDENTIAL
Attaching the AC Power Cable
Retaining bale
AC power cord
Insert the power cable plug into a properly grounded 115V/120V electrical outlet.
Turn the power switch to the ON position.
supply.
To turn an AC system OFF, press the power supply switch to the OFF position or unplug the
power cords.
To turn a DC system OFF, disconnect the power source to the wires to de-activate the circuit.
All port LEDs should flash momentarily, usually in sequence, while the device performs
diagnostics. After the diagnostics are complete, the LEDs will be dark except for those that
are attached by cables to other devices. If the links on these cables are good and the
connected device is powered on, the link LEDs will light.
Table 7
provides more details on specific LED conditions after system start-up.
2
1
"Verifying proper operation"
Brocade FastIron GS and FastIron GS-STK Hardware Installation Guide
on page 36.)
53-1001783-01

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents