Situation of UPS-System before starting the Transfer Procedure to Maintenance Bypass:
The load is protected by PowerWave 33 running in normal operation. (The UPS is operating on
inverter).
1.
Using LCD panel, select the COMMANDS menu, choose command "LOAD TO
BYPASS" and transfer the load to mains. (for parallel operation is enough to give the
order in one of the units).
2.
Close Maintenance Bypass Switch IA1 (position ON). On a system with multiple UPS in
parallel close IA1 on each UPS.
3.
The message "MANUAL BYP IS CLOSED" will appear on the LCD and the mimic panel
will show as below:
LED Indicator
LINE 1
LINE 2
BYPASS
INVERTER
BATTERY
4.
Press simultaneously the two ON/OFF buttons on the UPS-control panel (PMD) on all
control panels.
On the LCD's message "LOAD OFF, SUPPLY FAILURE" will appear and the mimic panel
will show:
LED Indicator
LINE 1
LINE 2
BYPASS
INVERTER
BATTERY
5.
Open the Output Switch IA2, Input Switch IA4 and Bypass Switch IA3 on all UPSs
6.
Open battery fuses/breakers on the external battery cabinets or racks.
THE UPS SYSTEM IS STILL POWERED (DANGEROUS VOLTAGE).
NOTE

6.5.4 Load Transfer: from Maintenance Bypass to Inverter operations

This procedure describes the sequence of operations to be done in order to restart the UPS and
restore ON-LINE mode (Load on Inverter).
THE OPERATIONS DESCRIBED IN THIS CHAPTER MUST BE PERFORMED
BY A SERVICE ENGINEER FROM THE MANUFACTURER OR FROM AN
AGENT CERTIFIED BY THE MANUFACTURER.
WARNING!
Modifications reserved
Page 40/50
Colour
Green
Green
Green
RED
Green
Colour
Green
OFF
OFF
OFF
Green

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents