8.2

Commissioning the 3KC8 transfer switching equipment

After the 3KC8 transfer switching equipment has been connected to the main circuits, and
the control circuits have been successfully connected according to type and source, you can
commission the transfer switching equipment.
Requirements
● The transfer switching equipment is in the "Manual" position
Figure 8-6
● The handle is in the O position
Figure 8-7
● All cable lugs / busbars have been properly mounted
Figure 8-8
Manual, 08/2017, L1V30368969104A-02
8.2 Commissioning the 3KC8 transfer switching equipment
Switch in "Manual" position
Handle in the "O" position
Fastening the cable lugs / busbars
Commissioning