5.1.3

Load Transfer: from Inverter operation to Maintenance Bypass

If it is necessary to perform service or maintenance on the UPS it is possible to transfer the UPS to
MAINTENANCE BYPASS.
WARNING
Situation of UPS-System before starting the Transfer Procedure to Maintenance Bypass:
The load is protected by Conceptpower DPA™ running in normal operation. (The UPS-Module is operating on
inverter).
1.
Using LDC panel, select the COMMANDS menu and choose command "LOAD TO BYPASS" and
transfer the load to mains on control panel of any one of the three UPS-modules
On LCD panel "LOAD NOT PROTECTED" will appear.
2.
Close Maintenance Bypass Switch IA1 (position ON).
On LCD: "MANUAL BYP IS CLOSED" will appear and the mimic panel will show:
LED Indicator
LINE 1
LINE 2
BYPASS
INVERTER
BATTERY
3.
Press simultaneously the two ON/OFF buttons on the UPS-control panel (PMD) on all control panels.
On the LCD's message "LOAD OFF, SUPPLY FAILURE" will appear and the mimic panel will show:
LED Indicator
LINE 1
LINE 2
BYPASS
INVERTER
BATTERY
4.
Open Parallel Isolators IA2-1, IA2-2, IA2-3, IA2-4, IA2-5 (depending of the UPS frames).
5.
Open battery fuses/breakers on the internal (if any) and the external battery cabinets or racks.
!
NOTE!
!
NOTE!
THE OPERATIONS DESCRIBED IN THIS CHAPTER MUST BE
PERFORMED BY A SERVICE ENGINEER FROM THE MANUFACTURER OR
FROM A AGENT AUTHORIZED BY THE MANUFACTURER.
!
Colour
Green
Green
Green
RED
Green
Colour
Green
OFF
OFF
OFF
Flashing Green
THE UPS SYSTEM IS STILL POWERED (DANGEROUS VOLTAGE).
THE LOAD IS NOW SUPPLIED BY MAINS AND IS THEREFORE NOT
PROTECTED THROUGH THE UPS.
04-3008_S5_ABB_OPMCPDPA-S2_GB_121202
Printed in Switzerland – Modifications reserved
Section-5
Page 6/16 ABB

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents