Starting Up A System; Suggestions For Configuring And Installing The Equipment - Siemens SIMATIC S5 Manual

Interface of the programmable controller
Hide thumbs Also See for SIMATIC S5:
Table of Contents

Advertisement

S5-95U, SINEC L2
3.3

Starting Up a System

The following section contains suggestions for configuring and starting up a system containing
programmable controllers.
3.3.1

Suggestions for Configuring and Installing the Equipment

The equipment is often used as a component in a larger system. The suggestions contained in the
following warning are intended to help you install your programmable controller safely.
Warning
Adhere to any safety and accident-prevention regulations applicable to your
situation and system.
If your system has a permanent power connection (stationary equipment) that is
not equipped with an isolating switch and/or fuses that disconnect all poles,
install either a suitable isolating switch or fuses in the building wiring system.
Connect your system to a ground conductor.
Before start-up, if you have units that operate using the main power supply,
make sure that the voltage range setting on the equipment matches the local
main power voltage.
When using a 24-V supply, make sure you provide proper electric isolation
between the main supply and the 24-V supply. Use only power supplies
manufactured according to IEC 364-4-41 or HD 384.04.41 (VDE 0100, part 410).
Fluctuations or deviations of the supply voltage from the rated value may not
exceed the tolerance limit specified in the technical data. If they do, functional
failures or dangerous conditions can occur in the electronic modules or
equipment.
Take suitable measures to make sure that programs that are interrupted by a
voltage dip or power failure resume proper operation when the power is restored.
Make sure that dangerous operating conditions do not occur even momentarily.
If necessary, force an EMERGENCY OFF.
EMERGENCY OFF devices must be in accordance with EN 60204/IEC 204
(VDE 0113) and be effective in all operating modes of the equipment. Make
certain to prevent any uncontrolled or undefined restart when the
EMERGENCY OFF devices are released.
Install power supply and signal cables so that inductive and capacitive
interference can not affect the automation functions.
Install your automation system and its operative components so as to prevent
unintentional operation.
Automation equipment can assume an undefined state in the case of a wire
break in the signal lines. To prevent this, take the proper hardware and software
safety measures when linking the inputs and outputs of the automation
equipment.
EWA 4NEB 812 6112-02