6.3 - Boiling calibration (for boiling models)
The HydroTap
G4 Celsius is equipped with a self-calibrating program to adjust for altitude. On start up, the
®
controls take the system through a calibration process. Once this mode is complete the system reverts back
to normal operation.
Boiling
802149UK Celsius residential - Installation instructions -Jan 2016 v2.03
Commissioning
• Press [START] / [STOP] button to start and stop the filter
flush.
• Open the flush stop cock.
• Allow at least 10 litres of water to flush through the filter.
STOP
• Once the filter flush is finished, close the stop cock then
press [STOP] to end filter flush mode.
• Press [NEXT] for the boiling calibration screen (boiling
models).
Filter flush menu
• Press the [Calibrate] button and the system will
commence the boiling calibration procedure.
This will take approx 5-6 minutes.