INSTALLING OPTIONAL ACCESSORIES
6-8
EATON Powerware
Connect to
Port 1 (DB‐9) on
Customer Interface Panel
6.
Connect the SCM wiring to the terminal block using the terminations shown in
Table 6‐4.
Table 6‐4. SCM Wire Terminations
From SCM A
TB1‐4
TB1‐5
TB1‐6
TB1‐7
From SCM B (If Used)
TB1‐4
TB1‐5
TB1‐6
TB1‐7
7.
Contact your Eaton service representative for verification and testing of the SCM
and its connections prior to making connections to terminal strip TB2 shown in
Figure 6‐7.
8.
Repeat Steps 1 through 7 if you are installing another SCM.
9.
Secure the access plate on top of the UPS Input/Rectifier cabinet.
®
9315 UPS (500–750 kVA) Installation and Operation Manual
Figure 6‐6. Terminal Block Bracket
To UPS
TB3‐1
TB3‐2
TB3‐3
TB3‐4
To UPS
TB3‐5
TB3‐6
TB3‐7
TB3‐8
S
164201244 Rev E www.powerware.com
Fuse
Terminal
Block
(TB3)
Remarks
Twisted wires (4)
1–2 turns per 3"
Remarks
Twisted wires (4)
1–2 turns per 3"