INSTALLING OPTIONAL ACCESSORIES
6-6
EATON Powerware
Connect to
Port 1 (DB‐9) on
Customer Interface Panel
6.
Connect RIM wiring to the terminal block using the terminations shown in
Table 6‐3.
Table 6‐3. RIM Wire Terminations
From RIM A
TB1‐4
TB1‐5
TB1‐6
TB1‐7
From RIM B (If Used)
TB1‐4
TB1‐5
TB1‐6
TB1‐7
7.
Contact your Eaton service representative for verification and testing of the RIM
and its connections prior to making connections to J1 through J4.
You can order interface cables separately for connecting to the 15‐pin D‐sub
connectors.
8.
Repeat Steps 1 through 7 if you are installing another RIM.
9.
If you are installing an SCM in addition to an RIM, proceed to paragraph 6.3;
otherwise, secure the access plate on top of the UPS Input/Rectifier cabinet.
®
9315 UPS (500–750 kVA) Installation and Operation Manual
Figure 6‐4. Terminal Block Bracket
To UPS
TB3‐1
TB3‐2
TB3‐3
TB3‐4
To UPS
TB3‐5
TB3‐6
TB3‐7
TB3‐8
S
164201244 Rev E www.powerware.com
Fuse
Terminal
Block
(TB3)
Remarks
Twisted wires (4)
1–2 turns per 3"
Remarks
Twisted wires (4)
1–2 turns per 3"