Installation And Operation; Transportation And Installation; Installation Procedure; Table 5-1 How To Transport And Install The System - Toshiba G9000 SERIES Installation And Operation Manual

480/480 v 1000/1330/1500/1660/2000kva
Hide thumbs Also See for G9000 SERIES:
Table of Contents

Advertisement

5

Installation And Operation

5.1 Transportation and Installation

Table 5–1
Transportation
Transport unit with forklift or pallet
jack ONLY.
PROHIBIT
!
NOTE

5.2 Installation Procedure

A)
Note the Load Tolerance of the Floor
Refer to Table 5–2 for list of UPS weights.
UPS Capacity (kVA)
Weight (lb.)
B) Minimum Clearance Required for Ventilation
Right side
Left side
Back side
Top side
C) Space Requirement for Routine Maintenance
Allow for the following space at the time of installation.
Front
Sides
Back side
Top side
36
How to Transport and Install the System
Using the 2 or 4 pre-drilled holes in the each UPS
channel base*, anchor the unit using appropriate
hardware. (Not provided)
* 4x 4-holes bases and 3x 2-holes bases
Do not transport UPS cabinet laid horizontally.
Cabinets must be maintained upright within ± 15° of the vertical during
handling.
Floor shall be flat and level. 3 inches surrounding mounting holes
shall be flush with maintenance pad or floor.
Table 5–2 List of UPS Weights
1000
1330
6613
9,590
1 in. (25 mm) (not required when sidecars are used)
1 in. (25 mm) (not required when sidecars are used)
0.0 in. (0 mm)
24 in. (600 mm) (for air flow)
40 in. (1000 mm)
0.0 in. (0 mm)
0.0 in. (0 mm)
20 in. (500 mm)
G9000 1000-2000kVA Installation and Operation Manual 91469-007
Installation
1500
1660
2000
11,354
11,795
13,558

Advertisement

Table of Contents
loading