5

Installation and Operation

5.1 Transportation and Installation

Transportation
Transport unit with forklift or pallet
jack ONLY.
PROHIBIT
!
NOTE

5.2 Installation Procedure

A)
Note the Load Tolerance of the Floor
Refer to Table 5–2 for list of UPS weights.
B) Minimum Clearance Required for Ventilation
Right side
Left side
Back side
Top side
C) Space Requirement for Routine Maintenance
Allow for the following space at the time of installation.
Front
Sides
Back side
Top side
G9400 480V 1200-2000kVA Installation and Operation Manual 203078-001
Table 5–1
How to Transport and Install the G9400 System
Using the two (2) front & rear pre-drilled holes in
each UPS channel base*, anchor the unit using
appropriate hardware. (Not provided)
* (9, 11 or 13) x 2 holes bases
Do not transport UPS cabinets laid horizontally.
Cabinets must be maintained upright within ± 15° of the vertical during handling.
Floor shall be flat and level. 3 inches surrounding mounting holes shall be flush with
cabinet mounting rails.
Table 5–2 List of UPS Weights
UPS Capacity (kVA)
Weight (lb.)
1 in. (25 mm) (except when aligned with other cabinets in the system)
1 in. (25 mm) (except when aligned with other cabinets in the system)
0 in. (0 mm)
24 in. (600 mm) (for air flow)
40 in. (1000 mm)
0 in. (0 mm)
0 in. (0 mm)
24 in. (600 mm)
Installation
1200
1600
2000
7,275
9,750
11,470
37