5
INSTALLATION AND OPERATION
5.1
TRANSPORTATION AND INSTALLATION
Transportation
Transport unit with forklift.
CAUTION : Do not transport in a horizontal position. Cabinets must be maintained
CAUTION : Be sure to fix the UPS on the level ground definitely.
3.2 INSTALLATION PROCEDURE
A) Note the load tolerance of the floor
Refer to Table 3.2 for list of UPS weights.
B) Minimum clearance required for ventilation
Right side
Left side
Back side
Top side
C) Space requirement for routine maintenance
Allow for the following space at the time of installation.
Front
Sides
30
Table 5-1 How to transport and install the system
Using the pre-drilled 2 or 4 holes in the each UPS
channel base*, anchor the unit using appropriate
hardware. (Not provided)
* 4x 4-holes bases and 3x 2-holes bases
upright within +/- 15° of the vertical during handling.
Table 5-2 List of UPS weights
UPS Capacity (kVA)
Weight (lb.)
25 mm (1 inch) (not required when sidecars are used)
25 mm (1 inch) (not required when sidecars are used)
0.0 mm (0 inch)
600 mm (24 inches) (for air flow)
1000 mm (39 inches)
0.0 mm (0 inch)
G9000 Installation and Operation Manual – 61480-012
Installation
1000
6613