3

INSTALLATION AND OPERATION

3.1

TRANSPORTATION AND INSTALLATION

Transportation
Transport unit with forklift.
If carry by overhead crane, use four M12
eyebolts. (Not provided)
PROHIBIT
!
NOTE
3.2

INSTALLATION PROCEDURE

A) Note the load tolerance of the floor
Refer to Table 3.2 for list of UPS weights.
UPS Capacity (kVA)
Weight (lbs)
B) Minimum clearance required for ventilation
Right side
Left side
Back side
Top side
C) Space requirement for routine maintenance
Allow for the following space at the time of installation.
Front
Sides
Back side
Top side
G9000 Installation and Operation Manual

TABLE 3.1 How to transport and install the system

Using the pre-drilled four holes in the UPS
channel base, anchor the unit using
appropriate hardware. (Not provided)
Do not transport UPS cabinet laid horizontally.
Cabinets must be maintained upright within ± 15° of the vertical
during handling
.
TABLE 3.2 List of UPS weights
80
855
25 mm (1 inch) (not required when sidecars are used)
25 mm (1 inch) (not required when sidecars are used)
0.0 mm (0 inch)
500 mm (20 inches) (for air flow)
1000 mm (40 inches)
0.0 mm (0 inch)
0.0 mm (0 inch)
500 mm (20 inches)
Installation
100
160
225
855
1160
1230
37