6.
Procedure for Cable Connections for Parallel Operation System
(1) Confirm the number of units to be connected in parallel. Identify the input/output power
terminal blocks and control wire connections for parallel operation systems as shown in
the appropriate Figure 5-1 through Figure 5-4.
(2) Connect the external control wire and power wire.
!
Straight through, shielded CAT6 cables with metal shielded RJ-45 plugs
on both sides are to be used for the parallel control signal cables. Use of
any other cables could cause erroneous communication failures.
NOTE
a)
Control wire connection
Parallel configuration wiring (Refer to Figure 4-17 and Figure 5-7)
52L control signal from Toshiba Tie Cabinet (TTC) to UPS-n IOAU-19
(TN11-23, 24).
Parallel control signals, for TLAIN, TLAOUT, TLBIN, TLBOUT, CAIN, CAOUT,
CBIN, CBOUT, DIAIN, DIAOUT, DIBIN, DIBOUT as shown in Figure 5-7 and
Figure 5-8)
b)
Power wire connection
From UPS AC Output Terminals to Toshiba Tie Cabinet (TTC)
(Refer to Figure 5-1 through Figure 5-4,
Figure
When in Parallel Operation, the rectifier inputs to all G9000 UPS Systems in
the Multi-Module System (MMS)-must be fed from a single source at all times
including any operation of Automatic Transfer Switches. All G9000 bypass
inputs must also be fed from a single source at all times (not necessarily the
CAUTION
same source as the rectifier inputs).