5
INSTALLATION AND OPERATION
5.1
TRANSPORTATION AND INSTALLATION
Transport with forklift. If carry by overhead crane, use four eyebolts (Not provided)
* Use lifting eyes on landing cabinet only to lift landing cabinet by itself, not as part of assembled unit.
Install the unit using the four pre-drilled holes in the UPS channel base. Anchor the unit using appropriate hardware. (Not
provided).
PROHIBIT
!
NOTE
5.2
INSTALLATION PROCEDURE
A) Note the load tolerance of the floor
Refer to Table 5-2 for list of UPS weights.
B) Minimum clearance required for ventilation
Right side
Left side
Back side
Top side
C) Space requirement for routine maintenance
Allow for the following space at the time of installation.
Front
Sides
Back side
Top side
38
Table 5-1 Transport by Overhead Crane
Model
500kVA
4 x M20 Lifting Eyes
750kVA
4 x M24 Lifting Eyes
Do not transport UPS cabinet laid horizontally.
Cabinets must be maintained upright within ± 15° of the vertical during handling.
Table 5-2 List of UPS Weights
UPS Capacity (kVA)
Weight (lb.)
1 in. (25 mm) (not required when sidecars are used)
1 in. (25 mm) (not required when sidecars are used)
0.0 in. (0 mm)
24 in. (610 mm) (for air flow)
40 in. (1016 mm)
0.0 in. (0 mm)
0.0 in. (0 mm)
20 in. (500 mm)
UPS Cabinet
500
2,756
G2020 Series UPS Installation and Operation Manual – 94861-004
Landing Cabinet *
4 x M16 Lifting Eyes
4 x M16 Lifting Eyes
750
3,990