Commissioning
6.1
Function check
Make sure that all final checks have been completed before you start up your measuring
point:
• "Installation check" checklist → Page 43
• "Connection check" checklist → Page 51
Switching on the measuring device
Once the connection checks (see Page 51) have been successfully completed, it is
time to switch on the power supply. The device is now operational.
The measuring device performs a number of self-tests after power-on. As this procedure
progresses the following sequence of messages appears on the local display:
PROSONIC FLOW 93
START RUNNING
▼
PROSONIC FLOW 93
SW AMPLIFIER
V XX.XX.XX
▼
CURRENT OUTPUT
FREQUENCY OUTPUT
RELAY OUTPUT
STATUS INPUT
▼
SYSTEM OK
→
OPERATION
▼
Standard measuring mode commences as soon as power-on is completed. Various
measured value and/or status variables appear on the display (HOME position).
Note!
If start-up fails, an error message indicating the cause is displayed.
Start-up message
Current software version
List of installed input/output modules
Beginning of standard measuring mode