8.1 Checking the Installation

Completing the Installation
This chapter provides instructions on how to perform a final check of the installation
before power is applied to the drive.
ATTENTION: Only qualified electrical personnel familiar with the
construction and operation of this equipment and the hazards involved
!
should start and adjust it. Read and understand this manual in its
entirety before proceeding. Failure to observe this precaution could
result in severe bodily injury or loss of life.
Use the following procedure to verify the condition of the installation:
ATTENTION: DC bus capacitors retain hazardous voltages after input
power has been disconnected. After disconnecting input power, wait
!
five (5) minutes for the DC bus capacitors to discharge and then check
the voltage with a voltmeter to ensure the DC bus capacitors are
discharged before touching any internal components. Failure to
observe this precaution could result in severe bodily injury or loss of
life.
Step 1. Turn off, lock out, and tag the input power to the drive. Wait five minutes.
Step 2. Verify that the DC bus voltage is zero. Refer to section 9.3.
Step 3. If a function loss coast-stop push-button has been installed, verify that it
has been wired correctly. Be sure the factory-installed jumper at terminals
16 and 20 has been removed so that the coast-stop push-button will work.
ATTENTION: The user must provide an external, hardwired
emergency stop circuit outside of the drive circuitry. This circuit must
!
disable the system in case of improper operation. Uncontrolled
operation may result if this procedure is not followed. Failure to
observe this precaution could result in bodily injury.
Step 4. Remove any debris, such as metal shavings, from around the drive.
Step 5. Check that there is adequate clearance around the drive.
Step 6. Verify that the wiring to the terminal strip and the power terminals is correct.
Step 7. Check that the wire size is within terminal specification and that the wires
are tightened properly.