Section 11
Establishing connection and verifying the IEC 61850 communication
11.3
100
Verifying the communication
Connect your PC to the nearby switch and ping the connected IED and the
Substation Master PC, to verify that the communication is working (up to the
transport layer). If it is possible to see all of them, then they can see each other.
The best way to verify the communication up to the application layer is to
•
use a protocol analyzer, for example an Ethereal that is connected to the
substation bus, and
•
monitor the communication
1MRK 504 088-UEN C
Installation and commissioning manual