Check Of Trip And Trip Reset Timers - ABB RET670 Installation And Commissioning Manual

Hide thumbs Also See for RET670:
Table of Contents

Advertisement

Section 13
Verifying settings by secondary injection
13.7.5.3
162
UL1
UL2
UL3
UN
IEC07000108 V2 EN
Figure 65:
Connection of the test set to the IED for test of alarm levels,
trip levels and trip timer
where:
1
is three-phase voltage group1 (U1)
2
is three-phase voltage group2 (U2)
2.
Apply 1.2 · Ur (rated voltage) to the U1 and U2 inputs.
3.
Decrease slowly the voltage of in phase UL1 of the test set until the ALARM
signal is activated.
The ALARM signal is delayed with timer tAlarm
4.
Check the alarm operation level by comparing the differential voltage level at
ALARM with the set alarm level UDAlarm.
5.
Continue to slowly decrease the voltage until START signal is activated.
6.
Check the differential voltage operation level by comparing the differential
voltage level at START with the set trip level UDTrip.
7.
Repeat steps
1
to
2
Observe that the connections to U1 must be shifted to test another phase.
(UL1 to UL2, UL2 to UL3, UL3 to UL1)

Check of trip and trip reset timers

Procdure
to check the other phases.
1MRK 504 088-UEN C
UL1
UL2
1
UL3
UN
UL1
2
UL2
UL3
IEC07000108-1-en.vsd
Installation and commissioning manual

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents